OK, maybe you noticed that there isn't any scaffolding on the building yet. We were told that it would start going up this week but it seems that there is a little delay in the processing of some permit paperwork down at the ol' L&I office. Go figure. There was a regularly scheduled bi-weekly meeting with the Architect, Engineers and Contractors today and we've been assured that the permit issue is priority #1.
Meanwhile, they are still tackling the preliminary work in the attic and should begin working on the new electrical wiring next week.