Thursday, July 23, 2009

Good Progress...Weather Permitting


Chuck Pukanecz gave us the following update from yesterday's construction meeting:



"Truss installation above the nave remains on schedule, with only the final 10-foot section of hips descending to the chancel connection remaining. That area was fully opened up yesterday, and work is proceeding to build that section of truss-work in place.

Meanwhile, the EPDM rubber roofing material is about 75% installed and the new gutters are being quickly installed, making way for the detail work to begin on flashing and fascia board. Next will come painting, with the scaffolding still scheduled to be removed August 17.

Workers are also currently pealing the roofing layers off the Chancel, which is not being rebuilt, but will get a new, smooth layer of sheathing and new gutters and EPDM roofing.

All the scheduling remains weather-dependent. Workers lost Tuesday to rain, and will be working this Saturday to make up the time.

During our semi-weekly Construction Progress Meeting yesterday, construction manager John Farrell of J.S. Cornell & Sons informed the project team that timing is getting very tight. 'Right now,' he said, 'it’s up to the weather. We have no float. We’re hard up against it.'

After the meeting yesterday, the team headed back up to the roof to examine the one active chimney that vents from the boiler room. Like the ones that were removed, it’s an old masonry chimney showing lots of wear. After looking at the masonry budget for the project, we decided while the scaffolding is up to shore up that chimney. It will be wrapped in metal lathe and get a ¾-inch coat of new stucco, extending its active life for decades."